Project Schedule

2006
August: Begin construction of shuttle and regasification vessels (SRVs)

2008
July: Began pipeline construction
October: Completed pipeline construction

2009
May: Begin installation of buoy system, hot tap, and manifolds
August/September: Depending upon weather, complete construction
Late 2009: Prepare for arrival of first Shuttle Regasification Vessel (SRV)